ข่าวสาร

Cha Uat 60 MT/HR Factory Construction

กลับไปข่าว

Cha Uat 60 MT/HR Factory Construction In September 2024, we commenced the construction of our 6 th Processing Factory with capacity 60 mt FFB/ hour at our Cha Uat site in Nakhon Sri Thammarat. Foundation work for the fac…

image
Cha Uat 60 MT/HR Factory Construction

In September 2024, we commenced the construction of our 6th Processing Factory with capacity 60 mt FFB/ hour at our Cha Uat   site in Nakhon Sri Thammarat. Foundation work for the factory buildings and machinery is now underway, with the goal of having everything ready for erection and installation in 2025.

The target for commissioning will be in December 2025.

จองเมล็ดพันธุ์